Welcome to the 1st Construction Update for 312-314 West 43rd Street
Construction Update
Interior abatement work to continue within the existing building on site, at 310 West 43rd Street. Ground exploration in the parking lot will begin by mid-March, and will take approximately one week to complete. Mobilization work for demolition will also begin mid-March, and include the erection of protective sidewalk sheds and exterior hoists on the existing building.